FTTP delayed due open exception
- Subscribe to RSS Feed
- Mark Topic as New
- Mark Topic as Read
- Float this Topic for Current User
- Bookmark
- Subscribe
- Printer Friendly Page
- Plusnet Community
- :
- Forum
- :
- Help with my Plusnet services
- :
- My Order
- :
- FTTP delayed due open exception
FTTP delayed due open exception
10-11-2022 2:41 PM
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Report to Moderator
Hello,
FTTP install scheduled for 25/10. Openreach subcontractor turned up and installed the internals and the grey box on the exterior of the property. They were unable to connect the fibre from the pole to the property as the pole cannot be climbed due to a "D" label on it. Therefore a hoist is required.
Openreach scheduled the appointment for Saturday 5/11 but never showed up. I was then told by Plusnet they might come on the Sunday (didn't know openreach worked Sundays).
When I chased on the Monday 7/11, Openreach updated plusnet with the following:
Order has been delayed due to an open Exception named FTTP Faulty Plant D-Side tracking NI queue. Unfortunately Openreach could not complete work due to a fault on the distribution side network. An engineer with the required skills will be visiting as soon as possible to try to resolve the issue in the network. On behalf of Openreach we would like to apologise for the delay and for any inconvenience this may cause. Thank you for your patience. Hence, I would request you to check "View My Job Tracker" back on 14/11/22 for further update
I've rung again asking for information on what exactly this fault is, as I was told by the subcontractor that they just needed a hoist and the subcontractor (Kellys) don't have one in the area.
Whilst I wait for either an update, or the 14th whichever comes sooner, I was wondering if anyone could decipher what this openreach message actually means. The pole supplies FTTP to other houses, so that side of it must be working. The existing copper line to my property continues to work. Surely a hoist cannot be that much of a commodity that it takes over 2 weeks to arrange?!
Many Thanks
Re: FTTP delayed due open exception
19-11-2022 7:57 AM
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Report to Moderator
Can anyone point me to Openreach’s SLA for new installs?
As the install was started nearly a month ago and still not finished am I correct in thinking the automatic compensation of £5 odd a day applies in this case?
Thanks
Re: FTTP delayed due open exception
19-11-2022 10:04 AM
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Report to Moderator
Was the date in question a COMMITTED (promised) date or an ESTIMATED date? See Automatic Compensation | Help | Plusnet
- Compensation will be due if your service isn’t activated by 11.59pm on the date we promised you
- We'll pay you £5.25 for the missed activation day, and for every day after that until the day your service is activated
- If the activation is delayed because you've missed the appointment, the compensation calculation will stop. It will only start again if the activation isn’t completed during the next engineer visit
You need to have had a PROMISED date, not just an estimated date.
Also see "How it will be paid"...
"We'll add it as a credit to your account within 30 days of a missed appointment, activation of service, or fixing of the total loss of service fault."
"The maximum amount of compensation for a total loss of service fault or delayed activation is 60 days. If we can't fix your service after 30 days, you have the right to leave us with no termination charges."
In another browser tab, login into the Plusnet user portal BEFORE clicking the fault & ticket links
Superusers are not staff, but they do have a direct line of communication into the business in order to raise issues, concerns and feedback from the community.
If this post helped, please click the Thumbs Up and if it fixed your issue, please click the This fixed my problem green button below.
Re: FTTP delayed due open exception
19-11-2022 1:30 PM
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Report to Moderator
“ We're emailing you to update you on your broadband order.
The engineer appointment to activate your broadband service is confirmed for 25/10/2022. The engineer should arrive between 08:00 - 13:00.
Please ensure you are available to provide access for the engineer to carry out the work.”
And an engineer did turn up and fit the ONT. just hasn’t managed to cable from the pole to the CSP (I think it’s called) yet due to the fact Kelly’s don’t own a hoist and needed Openreach proper as it were.
Now the pole has been replaced the hoist is no longer needed so any contractor will do.
So I’m assuming this falls under the committed rather than estimated scenario.
Thanks again for the info
- Subscribe to RSS Feed
- Mark Topic as New
- Mark Topic as Read
- Float this Topic for Current User
- Bookmark
- Subscribe
- Printer Friendly Page
- Plusnet Community
- :
- Forum
- :
- Help with my Plusnet services
- :
- My Order
- :
- FTTP delayed due open exception